Hyperscale data centers use 2% of US electricity

Hyperscale data centers use 2% of US electricity

Summary

Hyperscale data centers in the United States used an estimated 68 to 99 terawatt-hours of electricity from May 2024 through April 2025, equal to 1.5% to 2.2% of U.S. electricity use. Their estimated electricity-related emissions were 21 million to 31 million metric tons of carbon dioxide, while the estimate excluded on-site power generation.

Key Facts

  • Researchers identified 403 hyperscale data centers with verified size and electrical capacity; their average capacity was about 40 megawatts.
  • The estimated electricity use was based on facilities operating from May 2024 through April 2025 and assumptions about how much of their capacity they used.
  • The estimated power use was comparable to the electricity use of Wisconsin or Indiana.
  • The 403 facilities accounted for an estimated one-third to one-half of U.S. data center electricity use in 2024.
  • About 54% of the electricity came from fossil fuel power plants, 25% from renewables, and 21% from nuclear power.
  • The estimated emissions equaled about 0.5% of U.S. carbon dioxide emissions from fossil fuels.
  • The emissions estimate did not include on-site generation, such as natural gas turbines used at an xAI data center in Tennessee.