Natural England urged Bristol City Council to reject a proposed 40MW AI datacentre at Avonmouth, citing risks to protected birds and habitats nearby. Weeks later, ministers threatened to abolish Natural England and the Environment Agency, while the Environment Agency had raised flood, water-use and pollution concerns about the site.Key Facts
- The proposed datacentre site is within 600 metres of the Severn Estuary special protection area.
- Natural England said noise from the project could disturb and displace rare and vulnerable bird species.
- Hallen Marsh, another protected site, is 270 metres from the proposed datacentre; Natural England said the developers had not included it in their noise assessment.
- The Environment Agency objected because the site is on a high-risk flood plain and raised concerns about safe refuge during a flood.
- The Environment Agency said developers had not provided information about water use or possible pollution from land contamination.
- More than 4,000 people objected to the datacentre’s construction.
- More than 300 datacentre projects were waiting to connect to the UK electricity grid, representing 73GW of demand.
- Ministers said the two agencies could be abolished, with their responsibilities transferred to ministers or devolved administrations.